Via East Midlands successfully bid for Phase 1 of the Section 278 highway works at the Field Farm residential development site in Stapleford. The client for the works is Westerman Homes who are based in Chilwell, Nottinghamshire.

The works comprised the construction of a new priority junction to provide the main access to the new residential development site as well as the upgrading of an existing mini-roundabout junction to improve capacity on the adjacent road network. The scope of the project also included new surface and foul water drainage together with a new street lighting system, pedestrian refuges and anti-skid surface treatments.

The value of the works was £268,000 and work commenced in October 2017 and was completed in February 2018. The client is very pleased with the standard of the work and Via hope to win the second phase of the highways work in 2019. Construction of the first new homes on the development site is expected to start in August 2018.